The project consisted of the fitout of levels 19 and 20 and incorporating level 18 into the exiting tenancy of Charter Hall, bringing the overall tenancy to 6000m2. Level 20 is the main entrance and client interface floor, level 19 being the common meeting level with lunch and meeting rooms and level 18 being information technology, training, and innovation.
The construction was undertaken in stages to allow for the continued occupation and operation of Charter Hall.
The new stairs to be installed between levels 18 and 19 were located where the existing inter-tenancy stairs were previously situated. This presented a few issues cutting a 3m*8m penetration below in an occupied area and an occupied building.
The high-end finishes included travertine wall cladding and floors, bespoke powder coated ceilings and bathrooms incorporating Caroma Smart Command. Furniture and fitments were reused and repurposed after a detailed survey was undertaken.
The workmanship of FDC is of a high standard, achieving the desired effect by utilising their expertise in planning and delivering a project.
Category
Construction (Commercial) » Interior Fitouts
Price
$7 Million - $8 Million
Year
2023
Company
FDC Construction & Fitout
Project
Charter Hall Head Office
Suburb
Sydney
Prize
Winner