This very large Aged Care Facility comprising 7, 3 & 4 storey buildings was completed (during covid disruptions) in the remarkably short time of 20 months.
The complex comprises a 100 bed RACF (Nursing Home) & 220 residential apartments (110 Independent Living Units & 110 Social and Affordable Housing Units).
The site was divided into 2 halves, each operating with its own foreman and site staff and separate contractors. Foundations (after bulk excavation) comprised bored piles, soldier piles and footings with AFS Rediwall system used for car park walls and tiered levels of the Nursing Home. Two tower cranes were used, supplemented by mobiles as needed.
Site complications included tree protection zones, unexpected rock, and a contaminated subgrade, a major HV power feed (to Minto) and a substantial storm water system both running through the site.
This large composite Anglicare Minto Development has been well planned and constructed by a very well organised Hansen Yuncken design and construction team.
Category
Construction (Commercial) » Aged Care Buildings
Price
$50 Million & OVER
Year
2022
Company
Hansen Yuncken Pty Ltd
Project
Anglicare Minto Development
Prize
Winner