Works included the refurbishment of 575 hotel rooms and the creation of 108 additional rooms within existing spaces of the hotel.
Construction was successfully carried out with 65% occupation maintained during building works which were programmed to coincide with the hotel ‘quiet’ periods, existing lifts were used as there was no external hoist allowed by the client. Long lead times for finishes, joinery and lighting were required to allow for order and delivery within the program. Ongoing liaison with hotel staff, loading dock access and hours of work were part of the successful undertaking of this project.
This project demonstrates the importance of a strong relationship between the client and the project teams.
Works were completed in just over 17 months.