This project consisted of constructing the suites directly above the existing MRI and PET facility, alongside two fully functioning operating theatres and immediately above a loading dock in use 24 hours a day, seven days a week at thirteen metres below. The structural loading of the existing building was close to its limits so a lightweight steel structure and Hebel panels were the solution. To maintain a dry facility was a major focus during construction.
Work commenced with minimal drawings and the design was finalised only with close co-operation, understanding and flexibility by all parties. There were a number of stages, all delivered to tight deadlines due to pre-booked surgery and medical procedures.
The Recovery/Endoscopy Suites were constructed under very difficult circumstances and to a very high standard of finish.
Category
Construction (Commercial) » Health Buildings
Price
UP TO $5,000,000
Year
2014
Company
Woollam Constructions
Project
Lismore Base Hospital Recovery/Edoscopy Suites
Prize
Winner