To enable construction sites to resume safely on 31 July, preparatory works can begin from 29 July. These works include:
- checking or maintaining installations or equipment
- cleaning, waste removal or waste management
- stocktaking or restocking
- delivery of materials or equipment
- servicing or installation of amenities
- relocation on the construction site of plant or equipment
- issuing permits or certificates
- establishing arrangements or procedures to help protect persons from COVID-19
- erecting fencing or hoarding
- inspections, including for technical reasons, or safety, including work, health and safety, or for valuations or other financial reasons
- removing water
- connecting power, fuel or services
- safety work, including work related to fire safety or electrical safety
- surveying or marking out
- training required to be carried out on the construction site.